Monitoring and control of the steam production system operating in a non-permanent supervision mode at 72 hours:
- Monitoring and control of the steam production system consisting of:
- Steam boiler 6 t/h, 12 Bar x 1 unit
- Steam boiler 3 t/h, 12 Bar x 2 units
- Pumping group
- Purge system
- Safety and protection elements
- Steam temperature monitoring
- Compressed air pressure monitoring
- Monitoring of recovered condensate quality from production
- Pumping group monitoring
- Water softening station monitoring
- Deaerator water level monitoring
- Condensate tank level monitoring
- Monitoring of electrical parameters in the main thermal plant switchboard
- Electricity consumption monitoring
- Optical and acoustic alarm
- Local display system (HMI)
- SCADA system